Remodeling journal
Residential Construction Contract Review
Review scope, payment, schedule, change orders, and Washington disclosure items in a residential construction contract before you sign.

A residential construction contract is the written agreement that says what will be built, what it costs, when it happens, and what happens when the plan changes. For a kitchen, bathroom, addition, or custom home in King or Pierce County, that document is the place to settle those points before anyone opens a wall. Read it with the contractor who will do the work, and do not sign a packet you have not walked through line by line.
Have a project in mind? Call Tubro Construction at (253) 216-2633.
This guide covers the review, not the hiring process and not the remodel sequence. If you are still choosing a company, start with how to hire a remodeling contractor in Western Washington. If you are still ordering the decisions that come before a price, use the home remodeling process. The pages below assume you already have a draft in front of you.
What a residential construction contract should name
Start with the parties and the property. The contract should name the homeowner, the contractor's legal business name, the job address, and the date. In Washington, a contractor who advertises or bids construction work must show a registration number. You can check that registration, the bond, and the insurance on file with the Department of Labor & Industries before you rely on the packet. Tubro Construction is a veteran-owned remodeling and general contracting company, founded in 2010, serving homeowners in King and Pierce Counties. Its registration number is TUBROCI900DR.
Then read the scope as if you were explaining the job to a neighbor. A useful scope says which rooms change, which work is included, and which work is not. "Remodel the kitchen" is not a scope. A scope names demolition, framing, cabinets, counters, plumbing and electrical fixture locations, flooring, paint, and whether appliances are owner-supplied. The same standard applies to a bathroom, an addition, or a new home. If a line is vague, ask for it in writing before you sign.
Washington also requires a specific homeowner disclosure on many residential jobs of $1,000 or more, before work starts. State law, RCW 18.27.114, calls for a Notice to Customer. It states the registration number, the bond or deposit on file, and the registration expiration date.
The notice warns that the bond may not cover a claim and that it is shared with other claimants. It also says you may withhold a stated retainage, and that unpaid suppliers or subcontractors may lien the property. You should receive it and sign that you received it. It is a disclosure, not a promise that a problem cannot happen.
Price type, allowances, and what is excluded
The price section should say how the number was built. A fixed price covers a described scope. An allowance is a placeholder for an item you have not selected yet, such as tile, fixtures, or appliances. If the allowance is a guess, the contract should say what happens when the real selection costs more or less. Ask whether tax, permit fees, and dumpster or haul-off costs sit inside the price or outside it.
Exclusions matter as much as inclusions. A kitchen price that does not mention moving a sink, opening a wall, or replacing a subfloor can grow the day those conditions appear. Put owner-supplied items on their own list so nobody assumes the contractor is buying them. Tubro's public process is upfront pricing with no hidden fees and a free estimate. That is a pricing stance, not a promise that an allowance or an unseen condition stays at the first number. The contract is where that difference gets written down.
Do not treat this page as a cost-plus guide. If the draft uses cost-plus, ask what "cost" includes, how the fee is calculated, and which records you will see. If you want a planning checklist before you request numbers, the home renovation checklist is the broader list. This section only asks whether the price in front of you matches the scope in front of you.
Payment, schedule, and written change orders
Read the payment schedule against the work, not against a calendar alone. A fair schedule ties draws to stages you can see, such as demolition complete, rough-in inspected, cabinets set, or substantial completion. Ask what the deposit covers and whether any amount is held until the final walkthrough. RCW 18.27.114 tells homeowners they may withhold a contractually defined percentage as retainage for a stated period. If you want that protection, it has to be in the contract. A verbal plan to "hold some back" is not retainage.
The schedule should name a start condition and a completion target, plus what moves those dates. Permit review, long-lead cabinets, and selections you have not made are common reasons a date slips. A date with no start condition is a wish. Tie the schedule to the same scope you already read, and note who tells you when a date changes.
Read the draws in order before you initial the page. A deposit that is most of the price, with the rest due at the start, leaves you little leverage if the job stalls. Stage payments that follow visible work are easier to check on a walkthrough.
Ask which documents come with each draw, such as a short progress note or a list of work finished that week. If retainage is part of the deal, the contract should say the percentage, the period it is held, and the condition that releases it. Leaving that blank means there is no retainage, no matter what was said in the estimate meeting.
A change order is a written revision to scope, price, or time. It should say what changed, what it costs, and whether the completion date moves, and both sides should sign it before the extra work proceeds. Do not approve field changes by text and assume the contract caught up. Change orders deserve their own process. Here, the only question is whether this contract requires them in writing. The general contractor page describes how Tubro coordinates a residential scope. The contract is still the document that locks that scope.
Compare the clauses before you sign
Use the table as a review pass. If a row is blank in the draft, ask for the missing line before you sign. None of these rows replaces advice from your own attorney or from Labor & Industries.
| Clause | What to confirm | Ask if it is missing |
|---|---|---|
| Parties and property | Legal business name, your name, job address, and date | Who is actually obligated to do the work? |
| Registration | Washington registration number you can verify | Where do I check the registration, bond, and insurance? |
| Scope and exclusions | Rooms, tasks, and work that is not included | Which drawing or selection list does this price follow? |
| Price and allowances | Fixed scope versus placeholders, and what sits outside the price | What happens when a selection beats the allowance? |
| Payment and retainage | Deposit, stage draws, and any amount held to the end | What work must be done before each draw? |
| Schedule | Start condition, target completion, and delay reasons | Who notifies me when the date moves, and how? |
| Change orders | Written approval of scope, price, and time before extra work | Can any change proceed without a signed revision? |
| Warranty | What is covered, for how long, and who to call | What is excluded, such as owner-supplied items? |
| Insurance and liens | Liability insurance on file, and how lien releases are requested | When do I receive releases from suppliers and subs? |
| Notice to Customer | The Washington disclosure, signed before work starts | Where is my copy of the disclosure statement? |
| Communication | One named contact after the job begins | Who do I call when a decision or a problem comes up? |
| Closeout | Final walkthrough, punch list, manuals, and final payment terms | What must be done before the last payment is due? |
Warranty, insurance, and the Washington notice
A warranty clause should say what the contractor stands behind, for how long, and how you start a claim. Workmanship and manufacturer warranties are not the same thing. A cabinet brand's warranty does not cover a loose install, and a workmanship warranty does not rewrite a product warranty. Ask what is excluded, including owner-supplied items and normal wear. Get the length and the contact path in the contract, not in a brochure.
Insurance and the bond are also easy to mix up. Washington requires registered contractors to be bonded and insured. The bond is a limited fund that can be claimed for certain losses. The Notice to Customer says it might not cover a claim. Other customers, suppliers, subcontractors, and taxing authorities can claim against that same bond.
Liability insurance is a separate filing. Hiring a registered contractor does not guarantee a trouble-free job. Labor & Industries says registration may provide protections that are not available otherwise. Its hiring a contractor steps say to verify the registration, compare written bids, and get a written contract you understand.
Read the lien language with the same care. If a supplier or subcontractor is not paid, the property may be liened, and a homeowner can end up paying twice for the same work. The statute says you may request original lien-release documents from each supplier or subcontractor, and that the contractor must provide further information about those documents if you ask. Put the timing of those releases next to the payment schedule so a draw does not outrun the paperwork.
Communication and closeout
Name the person you will talk to after the contract is signed. Tubro assigns one project manager to each project after design and selections are set, so scheduling, scope changes, and day-to-day questions go through one contact. The remodeling project manager article covers why that model helps. In the contract, look for the name or the role, how decisions are confirmed, and how a field question becomes a change order instead of a surprise.
Closeout is the last set of lines, and it is where rushed contracts go thin. A complete closeout names the final walkthrough, a written punch list, the time allowed to finish those items, and which manuals, warranties, and lien releases you receive before final payment. It should also say that final payment follows that list, not a verbal "we're done." If the job needs a permit, ask which inspections are required before that walkthrough. Requirements depend on the city and the scope, so the contract should not pretend one county rule covers every address in Western Washington.
For a new home or a whole-home renovation, the same clauses apply, with more drawings and more selections behind them. The custom home services page is the service overview. It is not a substitute for the contract review above. Keep the contract, the signed disclosure, the selections, and every change order in one folder you can still find a year later.
A short pass the night before you sign keeps the meeting useful. Use this order:
- Read the scope out loud and mark every line you cannot picture.
- Check that the allowance list matches the selections you have actually made.
- Confirm the payment lines add up to the stated price, including any amount held to the end.
- Note the start condition in your own words and ask the contractor to confirm it.
- If a city permit is part of the job, ask who submits it and whether work can begin before it is issued.
Write those answers into the draft, not into a side email that never gets attached.
Bring the questions to the same person who will build the job, not only to a salesperson who will disappear after the signature. Tubro's estimate step is a free estimate with upfront pricing, and an assigned project manager follows once design and selections are set.
Office hours for that first conversation are Monday through Friday, 7:00 AM to 4:00 PM. Use the call to test whether the draft already answers the table above. A contractor who will revise a vague line before you sign is easier to work with than one who says the details can wait until the job starts.
FAQ: questions before you sign
What is a residential construction contract?
It is the written agreement between you and the contractor for a home project. It should cover the scope, the price, the schedule, how changes are approved, and how the job is closed out. A verbal estimate is not that agreement.
What should I review before I sign?
Review the scope and exclusions, allowances, the payment schedule, retainage, the start and completion terms, the change-order rule, warranty, insurance, the Washington Notice to Customer, the person you will contact, and the closeout list. If a line is missing, ask for it in the draft.
Does Washington require a disclosure before work starts?
For many residential projects of $1,000 or more, RCW 18.27.114 requires a Notice to Customer before work starts. It discloses the registration number, the bond or deposit, and the expiration date, and it warns about bond limits, retainage, and liens. Signing it means you received the disclosure.
Is a registered contractor's bond enough to cover my project?
Do not assume that. The required notice says the bond or deposit might not cover a claim and is not for your exclusive use. Verify the registration with Labor & Industries, and use the contract's payment and lien-release terms as your practical protection.
Does requesting an estimate reserve an appointment?
No. Tubro's estimate request asks for an estimate. It does not reserve an appointment. The office follows up to schedule the next step.
Call (253) 216-2633 to talk through a project, or request a free estimate. The form asks for an estimate and does not reserve an appointment.
Bring your ideas. We’ll talk through the next step.
Tell us about your home, your project city, and what you would like to change.
Request a Free Estimate